17. Time distribution.
The time management should set down the time distribution of work before
the work is started for it to be effective. This was done with the
timetables set out in the initial and interim reports. The author, now
upon completion of the work, feels that these timetables and deadlines
were ambitious considering the amount of work that was required and the
level of work that was needed for other subjects. All the work that was
intended to be done was so but some pieces possible not to the detail that
the author was looking for.
| Work item |
Time (hrs) |
Percentage |
| Research |
25 |
6.7 |
| Design concept |
45 |
12.0 |
| Multisurf |
80 |
21.3 |
| Structure |
45 |
12.0 |
| Hydromax |
12.5 |
3.3 |
| Rig |
35 |
9.3 |
| VPP |
7.5 |
2.0 |
| AutoCAD |
55 |
14.7 |
| Write up |
50 |
13.3 |
| Other |
20 |
5.3 |
| Total |
375 |
100 |